An Austrian utility needed project controls, technical coordination on a project with real consequences for schedule and cost. Work finished inside the planned window with no safety incidents.
Challenge
Major equipment had to be replaced without losing market availability.
What we did
A staged outage plan and supplier coordination across a very short outage window.
Result
Work finished inside the planned window with no safety incidents.

Details
Project details
Client
An Austrian utility
Location
Austria, Tyrol
Duration
2022–2025
Capacity
2 large transformers + control system upgrade · approx. €45m
Our role
Project controls, technical coordination